Scope of Work

Works Planned for 2022:

  • Preliminary works on retaining walls at Unity Square
  • Temporary street lighting will be installed to meet required city standards.
  • Preliminary utility relocation work will continue in 2022
  • Limited roadway construction
  • Tree removals will occur along the alignment between 138 St & 102 St
    Read more about Marigold’s Tree Policy here.

LRT Stops & Stations

  • MacEwan Arts/112 St Stop at 112 St & 104 Ave.
  • The Yards/116 St Stop at 116 ST & 104 Ave.
  • Brewery/120 St Stop at 120 St & 104 Ave.

Our Commitment to Safety

  • To help ensure public safety, excavations open and accessible to the public will be fenced or supervised. Please be aware of hazards and avoid excavation sites.