Area 6
- 87 Ave & 163 – Anthony Henday Dr
Scope of Work
Works Planned for 2023:
- West Edmonton Mall and Misericordia Stations: Ground level and structure construction
- 87 Ave Elevated Guideway: Started in 2021, will continue until 2024
- Pier construction ongoing
- Elevated gantry and spans installation
- Drainage: (Summer-Fall)
- Roadways construction
- Retaining walls
- Fencing along 87 Ave
What you can expect
- Increased traffic and construction noise
- Marigold will endeavour to maintain two lanes of traffic in either direction; however, there will be occasional lane reductions while construction occurs
- Motorists can expect lanes to shift around the various work sites periodically
- Turn movements will be maintained
- There may be temporary lane closures and/or reduced accessibility to roads, pathways and driveways
- Pedestrian Access will be maintained during construction, however some detours may occur
- Please watch for wayfinding signage in the area for direction
- There will be ETS detours at times
- Most work will occur during daytime hours, however, occasional overnight work will be required
- This work will be completed by Marigold Infrastructure Partners and subcontracted crews
- Elevated Guideway Construction Information
LRT Stops & Stations
- Misericordia Station at 169 St & 87 Ave
- West Edmonton Mall Station at 174 St & 87 Ave
- Aldergrove/Belmeas Stop at 182 St & 87 Ave
Our Commitment to Safety
- To help ensure public safety, excavations open and accessible to the public will be fenced or supervised. Please be aware of hazards and avoid excavation sites