Area 6

  • 87 Ave & 163 – Anthony Henday Dr

Scope of Work

Works Planned for 2022:

  • Elevated Guideway construction will continue
    • Deep pile foundations
    • Pier construction
    • Guideway spans will begin to be installed
    • Approach spans at east and west ends of EG
    • WEM and MIS station columns
  • Drainage works
  • Roadway construction
  • Temporary street lighting will be installed to meet required city standards.
  •  Temporary traffic signals
  • Utility Complexes – site prep and conduits
  • Stops/Stations construction preparation- excavation, drainage, and conduits

What you can expect

  •  Increased traffic and construction noise.
  • There may be temporary lane closures and/or reduced accessibility to roads, pathways and driveways.
  • There will be temporary pedestrian and ETS detours at times
  • Most work will occur during daytime hours, however, occasional overnight work will be required
  • This work will be completed by Marigold Infrastructure Partners and subcontracted crews. 
  • Elevated Guideway Construction Information

LRT Stops & Stations

  • Misericordia Station at 169 St & 87 Ave
  • West Edmonton Mall Station at 174 St & 87 Ave
  • Aldergrove/Belmeas Stop at 182 St & 87 Ave

Our Commitment to Safety

  • To help ensure public safety, excavations open and accessible to the public will be fenced or supervised. Please be aware of hazards and avoid excavation sites.
Marigold Edmonton 87 Ave Guideway Final Rev1 render