Anthony Henday Bridge Rendering

Area 7

  • Anthony Henday Dr
04.01.2022 AREA 7
Images courtesy of the Valley Line West LRT Design Guide Version 4 published September 2020.

Scope of Work

Works Planned for 2023:

  • Anthony Henday Drive LRT Bridge started in December 2022 continuing until 2024
    • Work on the approaches.
    • Bridge construction begins January 2023.
    • Girder installation begins approximately mid-January 2024.
  • Construction of a wall to protect the transmission tower from construction activities
  • Expansion of worksites at south side of 87 Ave 

What you can expect

  • Increased traffic and construction noise
  • Dust, noise, vibrations, air quality impacts
  • There may be temporary lane closures and/or reduced accessibility to roads, pathways and driveways
  • This work will be completed by Marigold Infrastructure Partners and subcontracted crews

Our Commitment to Safety

  • To help ensure public safety, excavations open and accessible to the public will be fenced or supervised. Please be aware of hazards and avoid excavation sites
Marigold Edmonton 87 Ave Guideway Final Rev1 render

Have a question?

If you have a general question about the project please don’t hesitate to fill out our contact form.

Send us a message