WHOLE ALIGNMENT
AREA 1
(102 Avenue & 102-107 Street)
Herbicide use along 107 Street from 102 Avenue to 104 Avenue – June 25, 2025
Access Closure on 107 Street at 102 Avenue – June 12, 2025
Traffic Shift on 103 Avenue and 107 Street – June 2, 2025
Alley Construction near 102 Avenue between 105 Street and 106 Street – May 26, 2025
Traffic Shift on 107 Street between 102 Avenue and 104 Avenue – April 22, 2025
Mobilization of the 102 Avenue and 105 Street Construction Laydown Area – October 10, 2023
AREA 2
(104 Avenue & 107-121 Street)
Overnight Work on 104 Avenue between 105 Street and 107 Street – June 26, 2025
Access Closures on 104 Avenue at 106 Street – June 17, 2025
Traffic Shift on 121 Street at 104 Avenue – June 5, 2025
Overnight Work on 104 Avenue between 107 Street and 121 Street – May 22, 2025
Access Closures on 104 Avenue at 110 Street – April 29, 2025
Construction of the 107 Avenue Construction Laydown Area – April 21, 2023
AREA 3
(104 Avenue/Stony Plain Road & 121-139 Street)
Lane Closure on Stony Plain Road between 129 Street and 132 Street – July 3, 2025
Herbicide use on Stony Plain Road between 123 Street and 139 Street – June 25, 2025
Access Closure at 127 Street on Stony Plain Road – June 17, 2025
Reopening of 124 Street and Stony Plain Road Intersection – June 11, 2025
Access Closures on 105 Avenue between 124 Street and 125 Street – June 9, 2025
Access Closure at 125 Street on Stony Plain Road – June 9, 2025
Access Closures on Stony Plain Road at 122 Street (North) – April 3, 2025
Lane Closures on Stony Plain Road Between 121 Street and 129 Street – December 12, 2024
Mobilization of the 132 Street & Stony Plain Road Utility Complex – February 29, 2024
Mobilization of the 124 Street and Stony Plain Road Construction Laydown Area – October 10, 2023
AREA 4
(Stony Plain Road & 139-156 Street / 156 Street & Stony Plain Road – 99 Avenue)
Lane Reduction on 100 Avenue at 156 Street – June 26, 2025
Herbicide use along Stony Plain Road between 156 Street and 139 Street – June 25, 2025
Access Closure at 148 Street on Stony Plain Road – June 3, 2025
Access Closure at 150 Street on Stony Plain Road – June 2, 2025
Temporary Closure of 139 Street and 142 Street Intersections at Stony Plain Road – May 26,2025
Access Closures at 147 Street on Stony Plain Road – May 13, 2025
Status Update – Partial Closure of Stony Plain Road and 156 Street Intersection – May 12, 2025
Access Closures at 153 Street on Stony Plain Road – April 22, 2025
Sidewalk Removals on Stony Plain Road between 152 Street & 154 Street – April 14, 2025
Access Closures at 152 Street on Stony Plain Road – April 9, 2025
Access Closures at 143 Street on Stony Plain Road – April 4, 2025
Sidewalk Removals on Stony Plain Road between 143 Street & 148 Street – April 4, 2025
Temporary Partial Closure of Stony Plain Road and 156 Street Intersection – April 3, 2025
Mobilization of the 144 Street & Stony Plain Road Utility Complex – March 13, 2024
Mobilization of the Utility Complex at 156 Street & 100A Avenue – October 20, 2023
AREA 5
(156 Street & 99 Ave-Meadowlark Road / Meadowlark Road – 98 Ave & 163 Street)
Herbicide use along 156 Street from 100 Avenue to 163 Street at 87 Avenue – June 25, 2025
Herbicide use on 87 Avenue from 182 Street to 189 Street – June 13, 2025
Herbicide use on 156 Street from 100 Avenue to 90 Avenue – June 13, 2025
Access Closure at 96 Avenue and 98 Avenue (west) on 156 Street – May 12, 2025
Access Closure at 97 Avenue (west) on 156 Street – May 8, 2025
Access Closure at 93A Avenue (West) on 156 Street – May 2, 2025
Sidewalk and Asphalt Removals 156 Street Between 95 Avenue and 100 Avenue – April 8, 2025
Temporary Closure of Meadowlark Road between 87 Avenue and 88A Avenue – April 3, 2025
Mobilization of the Meadowlark Road & 89 Avenue (Utility Complex) – February 29, 2024
Mobilization of the 156 Street & 94 Avenue (Utility Complex) – February 29, 2024
Mobilization of the 156 Street and 95 Avenue construction laydown area – July 26, 2021
AREA 6
(87 Avenue & 163 Street- Anthony Henday Drive)
Elevated Guideway Span Installation on 178 Street at 87 Avenue – July 7, 2025
Access Closure at 172 Street on 87 Avenue – June 26, 2025
Drainage Works on 87 Avenue between 170 Street and 175 Street – June 24, 2025
Traffic Shift on 87 Avenue between 175 Street and 181 Street – May 30
Sidewalk Construction on 87 Avenue between 161 & 164 Street – May 12, 2025
Access Closure at 182 Street on 87 Avenue – April 28, 2025
Drainage and Road Works along 87 Avenue between 182 Street and 189 Street – April 28, 2025
Drainage and Road Works on 87 Avenue between 170 Street and 159 Street – November 19, 2024
South Service Road Closure on 87 Ave Between 161 Street and 163 Street – July 31, 2024
Mobilization of the 190 Street & 87 Avenue – March 13, 2024
Mobilization of the 182 Street & 87 Avenue (Utility Complex) – February 29, 2024
Mobilization of the Misericordia Station Utility Complex – February 29, 2024
AREA 7
AREA 8
(87 Avenue /Webber Greens Drive & Anthony Henday Drive – Lewis Farm Transit Centre)
Herbicide use Lewis Farms Transit Centre and ETS Terminal – June 25, 2025
Construction of the Lewis Farms Construction Laydown Area – April 19, 2022
Closure of 199 Street south of Lewis Farms Transit Centre – November 1, 2021
AREA 9
(Gerry Wright Operations & Maintenance Facility-OMF / 75 Street & Whitemud Drive)
Construction of Gerry Wright Operations and Maintenance Facility, Stage 2 is ongoing.
Construction of the Gerry Wright Operations & Maintenance Facility B